Measure the service, not one invoice

A transport quote is one part of the cost of fulfilling an order. Extra handling, storage, urgent replenishment and product loss can change the result. Improving one invoice while increasing costs elsewhere may leave the business paying more overall.

Total cost to serve brings the relevant costs into one comparison. Start with a defined service: which products, which locations, what volume and what delivery conditions? Without that definition, two apparently different prices may be buying different outcomes.

Build a comparable baseline

Choose a representative period and record transport, storage, handling, inventory and product-loss costs. Include relevant administrative and implementation costs. State how shared costs are allocated and use a consistent unit, such as a fulfilled order or a delivered case.

Record the service baseline alongside spend: delivery reliability, order accuracy and product condition. Comparing cost without these measures can hide a deterioration in the experience customers receive.

Find opportunities without weakening control

EPA freight-efficiency guidance identifies load planning, route design and reduced unnecessary idling as useful areas to examine. FAO also explains why appropriate temperature control and storage matter for limiting food loss. These are general principles, not GTC savings claims. [1][2]

An improvement review can therefore examine delivery frequency, waiting time, vehicle utilisation and handling steps. Any change must still respect product requirements and agreed service conditions. Avoid reducing cooling or combining incompatible products simply to make a cost line smaller.

An illustrative calculation

The following numbers are fictional and are not GTC results. Assume 100,000 cases are delivered in a defined period under unchanged service conditions. Baseline recurring cost is EGP 1,000,000, or EGP 10 per case. A proposed operation costs EGP 940,000 for the same volume, or EGP 9.40 per case.

That suggests a recurring reduction of EGP 60,000, or 6%. But if implementation costs EGP 40,000 in the first period, its total becomes EGP 980,000. First-period net savings are therefore EGP 20,000, or 2%. The 6% recurring reduction applies only if the new cost level continues and the service remains comparable.

Separate savings from avoided costs

A measured saving reduces actual comparable expenditure. Cost avoidance describes an expense that might otherwise have occurred. Both can matter, but they should not be combined without explanation or presented as the same financial result.

Check changes in volume, product mix, fuel prices and service scope before attributing an improvement to a new process. Report the period, calculation method and material exceptions. If the data cannot isolate an effect, describe the limitation rather than present an unsupported percentage.

Make the improvement sustainable

A credible efficiency case explains the starting point, what changed, the investment required and what happened to customer service. Review results after implementation and agree who owns the next corrective action.

This framework can support an initial efficiency discussion with GTC. The appropriate opportunity and any expected benefit depend on the actual operating data; they should be established through assessment rather than assumed from a general example.